A stope gully underground, with air and water lines running to the face

Compressed air · A PGM mine, Limpopo

Compressor scheduling and a compressed-air wastage roadmap

Compressors were running to a fixed pattern, not to demand. We showed what matching supply to the mining cycle would save, and what to fix first.

R7M to R10M

a year, opportunity identified

How to read this figure

Modelled figure. It is what our analysis predicts, not a measured saving.

2024 to 2025

The problem

What was going wrong.

Compressed air was the mine's most expensive utility, and much of it was being produced when nobody was drilling. Pressure at the face was still too low during the drilling shift.

What we did

  • Profiled compressed-air demand across the 24-hour mining cycle.
  • Modelled compressor schedules against that demand.
  • Sized the supply lines, comparing steel and HDPE pipe, to recover pressure at the face.
  • Ranked the fixes by cost and return into a step-by-step plan.

The result

What the client got.

The mine received a prioritised plan with the cost and expected return of each step.

What we found

  • Compressor scheduling alone was modelled at R7M to R10M a year.
  • A first package of fixes costing about R1.35M was estimated to return R7.5M to R9.5M a year.
  • The package: compressor scheduling, crosscut isolation valves, water level-control valves and half-level flow meters.

More work

Other case studies.

All case studies
A mine on the skyline at dawn

Let's find what your mine is losing.

Tell us about the site. We will come and look, and tell you plainly what we think it is worth fixing.